16,000 kVA OLTC Oil Immersed Transformer 35kV/10.5kV

16,000 kVA 35kV OLTC transformer loaded on heavy transport truck — view from workshop toward factory gate, Zhongxin General April 2026
On April 11, 2026, Zhongxin General completed delivery of one 16,000 kVA on-load tap-changing oil-immersed transformer to a dedicated 35kV industrial zone substation. This unit will serve as the main step-down transformer for the entire zone, taking dedicated 35kV incoming power and stepping it down to 10.5kV for zone-wide distribution. This case study documents the complete production process from core stacking through factory acceptance testing to dispatch

Full Case Study for Dedicated Industrial Zone Power Supply

Project Snapshot

Background: Powering an Entire Industrial Zone

Industrial zones present a unique power supply challenge. Unlike a single factory with predictable load patterns, an entire zone must accommodate multiple tenants — each with different equipment, varying demand profiles, and independent start-up schedules. The main incoming substation transformer must therefore handle not only high total capacity (16,000 kVA in this case) but also significant voltage fluctuations as tenants come online and offline throughout the day.

This transformer was commissioned by a dedicated industrial zone operator to serve as the primary step-down transformer for their entire facility. The zone receives a dedicated 35kV supply line from the regional grid. This transformer steps that voltage down to 10.5kV, which is then distributed across the zone to multiple terminal distribution transformers, each further stepping down to 0.4kV for individual factory connections.

The critical requirement for this application is voltage stability under varying load conditions. With multiple tenants connecting and disconnecting, the primary transformer must maintain a stable 10.5kV output regardless of fluctuations on the 35kV incoming supply or changes in zone-wide load.

This is why the client specified an on-load tap-changing (OLTC) transformer — enabling continuous voltage regulation without ever interrupting power to the zone.

Complete Production Documentation

The following images document the complete manufacturing process of this 16,000 kVA OLTC transformer — from the first silicon steel lamination to the final dispatch convoy.

1. Core Stacking — The Foundation of Efficiency

Workers stacking silicon steel core laminations for 16,000 kVA 35kV OLTC oil-immersed transformer — Zhongxin General factory
Core lamination stacking in progress. Grain-oriented silicon steel sheets are stacked in step-lap configuration to minimise no-load losses — the foundation of the transformer’s long-term energy efficiency performance.

The core is the heart of any transformer’s energy efficiency. For this 16,000 kVA unit, high-permeability grain-oriented silicon steel was used, stacked in a step-lap configuration to reduce no-load losses and magnetising current. The quality of core stacking directly determines the transformer’s efficiency over its 30+ year service life.

2. Winding Assembly and Drying

Transformer windings prepared for drying process — 16,000 kVA 35kV OLTC power transformer, Zhongxin General
Completed winding assemblies staged for drying. Removing residual moisture from the cellulose insulation system before oil-filling is critical for long-term dielectric strength and service life.

The winding assemblies are manufactured from high-purity electrolytic copper. Before oil-filling, the entire winding assembly undergoes drying to remove residual moisture from the cellulose insulation system. Any remaining moisture would compromise dielectric strength and accelerate insulation aging over time.

3. Tap Lead Connections — The OLTC Interface

Close-up of tap lead connections on winding assembly — 16,000 kVA 35kV OLTC transformer manufacturing, Zhongxin General
Close-up of the tap lead connections on the winding assembly. These leads connect to the on-load tap changer mechanism, enabling voltage regulation across all tap positions under full load without supply interruption.

These leads connect the winding to the on-load tap changer mechanism. The OLTC allows the transformer to adjust its voltage ratio under full load — selecting different tap positions on the 35kV winding to maintain stable 10.5kV output regardless of grid voltage variation.

4. Winding-to-Core Mechanical Fixing

Winding assembly secured to core clamping frame — 16,000 kVA 35kV OLTC transformer active part assembly, Zhongxin General
Detail of the winding assembly secured to the core clamping frame. Precise mechanical fixturing at this stage determines short-circuit withstand performance and resistance to vibration throughout the transformer’s service life.

Precise mechanical fixturing at this stage determines the transformer’s ability to withstand short-circuit forces and resist vibration throughout its service life. The clamping pressure must be sufficient to prevent winding movement under fault conditions but not so high as to damage insulation.

5. Complete Active Part — Before Lead Installation

Complete active part assembly before lead installation — 16,000 kVA 35kV OLTC oil-immersed transformer, Zhongxin General
The completed active part — core and windings fully assembled — photographed before lead installation begins. This stage represents the structural and electrical heart of the transformer prior to tank assembly.

This is the structural and electrical heart of the transformer — core and windings fully assembled, photographed before lead installation begins. From this point, the active part will be lowered into the tank, leads will be connected to the bushings, and the unit will be prepared for oil-filling.

6. Tank Fabrication — Base Detail

Tank base structure detail — 16,000 kVA 35kV OLTC oil-immersed power transformer fabrication, Zhongxin General
Detail of the transformer tank base structure. The base is engineered to support the full weight of the active part and insulating oil, and to distribute load evenly for both fixed foundation and transport configurations.

The tank base must support the full weight of the active part (approximately 8-10 tonnes for this capacity) plus approximately 8,000-10,000 litres of insulating oil. The base is also engineered to distribute load evenly for both permanent foundation mounting and heavy transport configurations.

7. Tank Fabrication — Upper Section

Upper tank section with fittings — 16,000 kVA 35kV OLTC oil-immersed power transformer, Zhongxin General
Upper section of the transformer tank showing the main cover plate, fitting penetrations, and sealing surfaces. Tank integrity at this level is critical for long-term oil containment and moisture exclusion.

The upper tank section showing the main cover plate, fitting penetrations for bushings and instrumentation, and sealing surfaces. Tank integrity at this level is critical for long-term oil containment and moisture exclusion.

8. Oil Drain Valve Detail

Oil drain valve detail on transformer tank — 16,000 kVA 35kV OLTC power transformer, Zhongxin General
Close-up of the oil drain valve fitted to the transformer tank. Full oil drainage capability is required for insulating oil sampling, oil replacement, and transport preparation — a routine maintenance access point throughout the transformer’s service life.

The oil drain valve is a routine maintenance access point throughout the transformer’s service life — used for insulating oil sampling, oil replacement, and transport preparation. For this project, the valve will be accessed during site commissioning for oil testing before the unit is energised.

9. Conservator Tank Installation

Oil conservator installation in progress — 16,000 kVA 35kV OLTC oil-immersed power transformer, Zhongxin General
Installation of the oil conservator tank. The conservator maintains constant oil pressure in the main tank and accommodates thermal volume changes, while the breather system prevents atmospheric moisture from entering the oil circuit.

The conservator (oil expansion tank) maintains constant oil pressure in the main tank and accommodates thermal volume changes as the transformer heats up and cools down during load cycles. The breather system, fitted with a silica gel air dryer, prevents atmospheric moisture from entering the oil circuit.

10. Conservator and Bushings — Fully Installed

Upper view of transformer with conservator and HV/LV bushings fully installed — 16,000 kVA 35kV OLTC power transformer, Zhongxin General
Upper view of the transformer with conservator tank and high/low voltage connection bushings fully installed. At this stage the transformer’s external configuration is complete and ready for final assembly of protection and monitoring fittings.

With the conservator tank and HV/LV bushings fully installed, the transformer’s external configuration is complete. The high-voltage bushings (35kV side) are noticeably larger and taller than the low-voltage bushings (10.5kV side) — a visual indicator of the voltage step-down function.

11. OLTC Control Cabinet — Side View

On-load tap changer control cabinet side view — 16,000 kVA 35kV OLTC oil-immersed power transformer, Zhongxin General
Side view of the on-load tap changer (OLTC) control cabinet. This unit drives the tap selection mechanism, enabling continuous voltage regulation under full load — adjusting the 35kV input across all tap positions to maintain stable 10.5kV output regardless of grid voltage variation.

The OLTC control cabinet houses the motor drive mechanism that selects tap positions. The control cabinet can be operated locally (via manual controls) or remotely (via SCADA interface), allowing the zone operator to adjust voltage without dispatching personnel to the substation.

12. Fan Cooling Control Cabinet

Forced-air cooling fan control cabinet — 16,000 kVA 35kV OLTC oil-immersed power transformer, Zhongxin General
The forced-air cooling fan control cabinet. The export-specification units are fitted with bilingual or full English labelling on all indicators and controls — a standard requirement for international project commissioning and ongoing O&M by non-Chinese-speaking site teams.

13. Factory Acceptance Test Preparation

Factory acceptance test preparation — 16,000 kVA 35kV OLTC oil-immersed power transformer, Zhongxin General
The completed transformer staged for factory acceptance testing. Every unit undergoes a full test programme — winding resistance, voltage ratio, no-load loss, load loss, short-circuit impedance, and dielectric tests — before leaving the factory.

Before any transformer leaves the factory, it must pass a comprehensive test programme. This unit underwent:

14. Dispatch — Loaded and Secured (View from Factory Gate)

16,000 kVA 35kV OLTC transformer loaded on heavy transport truck — view from factory gate toward workshop, Zhongxin General April 2026
The transformer main body, cooling fans, and radiator panels fully secured on the heavy transport vehicle — viewed from the factory gate looking toward the workshop. Dispatch date: April 11, 2026.

On April 11, 2025, the completed transformer — main body, cooling fans, and radiator panels — was loaded onto a heavy transport vehicle. This view is taken from the factory gate, looking back toward the workshop. The dimensions of a 16,000 kVA transformer require careful load distribution and multiple securing points to meet road transport regulations.

15. Dispatch — Loaded and Secured (View from Workshop)

16,000 kVA 35kV OLTC transformer loaded on heavy transport truck — view from workshop toward factory gate, Zhongxin General April 2026
The same loading scene photographed from inside the workshop looking toward the factory gate — showing the full transport configuration of the transformer, radiators, and cooling fans ready for road departure on April 11, 2026.

This second view, taken from inside the workshop looking toward the factory gate, shows the full transport configuration. The radiator panels are mounted on both sides of the main tank, and the cooling fans are secured in position. The unit is now ready for the road journey to the industrial zone site.

Project Significance: Reliable Power for Industrial Growth

This 16,000 kVA OLTC transformer is not just a piece of equipment — it is the electrical backbone of an entire industrial zone. Every factory within the zone, from heavy manufacturing to light assembly, depends on this single unit to deliver stable, reliable power at the correct voltage.

The on-load tap-changing capability is particularly critical for this application. Industrial zones experience wide load swings throughout the day — morning start-ups, mid-day peak loads, evening shut-downs — and the 35kV incoming supply can also vary. The OLTC automatically adjusts the tap position to maintain a stable 10.5kV output regardless of these fluctuations, ensuring that every connected factory receives power within acceptable voltage tolerances.

Once this transformer is commissioned on site, the zone’s complete power chain will be:

35kV Grid Supply

[THIS TRANSFORMER] — 35kV → 10.5kV (OLTC regulated)

the whole industril zone-wide 10.5kV Distribution Network

Terminal Distribution Transformers — 10.5kV → 0.4kV

Individual Factory Connections

International Standards Compatibility

Zhongxin General designs and manufactures power transformers to multiple international standards:

Special environmental specifications (high altitude, tropical humidity, seismic zones, extreme cold) are available on request.

Xinjin People’s Hospital Power Distribution System (dry type transformers and switchgears)
→ 8,000 kVA OLTC Transformer Export to DR Congo — International logistics and nitrogen transport
31,500 kVA OLTC Transformer — Jingten Energy 35kV Substation
63 MVA/110 kV OLTC Transformer — Ningxia LNG & Helium Project

About Zhongxin General Electric Energy Co., Ltd.

Zhongxin General is a Sichuan-based National “Little Giant” Enterprise and National High-Tech Enterprise manufacturing oil-immersed and dry-type power transformers (30 kVA to 100 MVA, 0.4 kV to 138 kV), medium-voltage switchgear, prefabricated substations, microgrids, and energy storage systems. The company is a strategic partner of State Grid Corporation of China and China Southern Power Grid.

Enquire About Your Project

Whether you need an OLTC transformer for an industrial zone, a standard distribution transformer for a commercial facility, or a complete prefabricated substation for a remote site — Zhongxin General’s engineering team can design a solution for your specific requirements.

Contact Our Engineering Team
View Power Transformer Product Range
Browse All Case Studies

Kevin Z

About the Author

Kevin Z

Kevin holds dual academic backgrounds in Electrical Engineering and English Language. He is a core member of two selective professional communities — a group of elite electrical engineers and a high-level ESL learning circle. With over 15 years of experience in international marketing and sales, Kevin currently serves as Director of International Trade at Zhongxin General.

Beyond his corporate role, Kevin is also a key member of a distinguished export business network based in Ningbo, Zhejiang — one of China’s most dynamic trade hubs. Through this circle of outstanding export enterprises, he gains deep exposure to best practices in business operations, management strategies, and global trade — insights he brings directly to his work and writing.

16,000 kVA 35kV OLTC transformer loaded on heavy transport truck — view from workshop toward factory gate, Zhongxin General April 2026

16,000 kVA OLTC Oil Immersed Transformer 35kV/10.5kV

On April 11, 2026, Zhongxin General completed delivery of one 16,000 kVA on-load tap-changing oil-immersed transformer to a dedicated 35kV industrial zone substation. This unit will serve as the main step-down transformer for the entire zone, taking dedicated 35kV incoming power and stepping it down to 10.5kV for zone-wide distribution. This case study documents the complete production process from core stacking through factory acceptance testing to dispatch

Read More »
KYN28-12 switchgear loaded on truck reversing to factory yard — Zhongxin General Sichuan Ruibai project Zigong April 1 2026

22 KYN28-12 HV Switchgear + 2 SCB18 Dry-Type Transformers Shipped to Zigong City for CATL Supply Chain Project

On the early evening of April 1, 2026, Zhongxin General dispatched 22 KYN28-12 10kV switchgear panels and 2 SCB18-1600/10.5 cast resin dry-type transformers (5.69% impedance, 3,430 kg each, Dyn11) to Sichuan Ruibai New Energy Materials Co., Ltd. in Zigong, Sichuan — a front-end supplier to CATL’s battery supply chain. The transformers meet GB 20052-2024 Tier 1 efficiency standards. Full technical specifications and project documentation.

Read More »
Assembled prefabricated modular substation for Aktau port Kazakhstan — 15 m × 10.5 m × 3.7 m complete unit, Zhongxin General Chengdu

Custom Prefabricated Modular Substation for Aktau Port, Kazakhstan — A Belt & Road Power Infrastructure Case Study

Zhongxin General engineered a purpose-built 2×800 kVA prefabricated modular substation for Kazakhstan’s Aktau container port — a Belt & Road flagship hub on the Caspian Sea. The 15 m × 10.5 m × 3.7 m unit was split into 5 factory-complete transport modules and delivered 4,500 km overland via Horgos, featuring 14-unit KYN28-12 switchgear, own-manufactured ZHONGXIN GENERAL dry-type transformers, and a climate-adaptive environmental control system engineered for Aktau’s harsh coastal conditions.

Read More »
SZ13-8000/120 OLTC transformer at Lianyungang port ready for vessel loading — China export DR Congo view 1

When Your Transformer Doesn’t Fit the Ship: A Real Lesson in Large Equipment Export Logistics from China

A real account of what happened when the allocated vessel space at Shanghai Port could not accommodate an 8,000 kVA 120kV OLTC transformer main tank during export to a DR Congo power station project — the rerouting to Lianyungang Port, the two-and-a-half-month delay, and the practical lessons learned. Written for international buyers and EPC procurement teams planning to source large power transformers from China. Includes recommendations on vessel space booking, port selection for heavy-lift cargo, nitrogen transport verification, and split shipment planning.

Read More »
Heavy transport truck carrying SZ13-8000/120 OLTC transformer leaving Zhongxin General factory 7PM, 16th, September 2025

8000kVA 120kV OLTC Power Transformer Exported to DR Congo — Full Project Case Study

Zhongxin General exported a SZ13-8000/120 on-load tap-changing power transformer — 8,000 kVA, 120kV class, 27.8 tonnes total weight — to a power station project in the Democratic Republic of Congo. Independent quality inspection was personally overseen by a former General Manager of Chint Electric’s transformer division. The shipment navigated a real-world logistics challenge when vessel space constraints at the original port required rerouting via Lianyungang. The unit arrived at Mtwara Port, Tanzania on February 4, 2026, with package condition verified as no damage. Switchgear supplied as part of the complete package.

Read More »
Zhongxin General factory main gate and front facade — Xinjin District Chengdu Sichuan China

From ZX TRANSFORMER to ZHONGXIN GENERAL: Our Brand Has a New Name

Effective March 2026, Sichuan Zhongxin General Electric Energy Co., Ltd. has officially rebranded its international identity from ZX TRANSFORMER to ZHONGXIN GENERAL — aligning with our product nameplate identity and reflecting an expanded portfolio that now spans transformers, switchgear, prefabricated substations, energy storage, and EV charging infrastructure. Our website, legal entity, products, team, and certifications remain unchanged.

Read More »

Get In Touch Now

Thanks for leaving message to us, in workdays your message will be replied in 24 hours. Please be specific on your needs, so we can reply targetedly. 

Send a Message to Us

Thanks for leaving a message to us, we will reply as soon as possible! The more detailed your message is, the more targeted reply we will make!

Get In Touch Now

Thank you for leaving message to us, the more specific and detailed your message is, the more targeted reply you will receive, your message usually will be replied within 24 hours!